ITEM DESCRIPTION |
QUANTITY |
UNIT |
|
EXTENSION |
|
|
|
|
|
General
conditions |
|
|
|
|
General
conditions |
1 |
$ 4,000.00 |
ea. |
$ 4,000.00 |
Trucking
and material handling |
1 |
$ 300.00 |
ea. |
$ 300.00 |
Supervision |
1 |
$ 3,000.00 |
ea. |
$ 3,000.00 |
Equipment rentals |
1 |
$ 300.00 |
ea. |
$ 300.00 |
Dumpster |
1 |
$ 1,500.00 |
ea. |
$ 1,500.00 |
Barricades and protection |
1 |
$ 300.00 |
ea. |
$ 300.00 |
Nails, fasteners, etc. |
1 |
$ 100.00 |
ea. |
$ 100.00 |
Miscellaneous items |
1 |
$ 500.00 |
ea. |
$ 500.00 |
Demolition |
|
|
|
|
Selective demolition |
6 |
$ 200.00 |
man day |
$ 1,200.00 |
Sitework |
|
|
|
|
Site Layout |
1 |
$ 150.00 |
ea. |
$ 150.00 |
Rock excavation |
35 |
$ 100.00 |
CY |
$ 3,500.00 |
Backfill |
40 |
$ 20.00 |
CY |
$ 800.00 |
Fine grading |
1 |
$ 200.00 |
LS |
$ 200.00 |
Topsoil and seed |
1 |
$ 500.00 |
LS |
$ 500.00 |
New
Vee-drainage swale on hill above addition |
1 |
$ 1,500.00 |
LS |
$ 1,500.00 |
New asphalt dished gutter behind addition |
40 |
$ 8.00 |
LF |
$ 320.00 |
New front wood stairs with 2 handrails |
1 |
$ 600.00 |
ea. |
$ 600.00 |
Concrete |
|
|
|
|
Footings |
5 |
$ 150.00 |
SY |
$ 750.00 |
Foundation walls |
16 |
$ 160.00 |
SY |
$ 2,560.00 |
Floor slab |
230 |
$ 5.00 |
SF |
$ 1,150.00 |
Basement steps |
12 |
$ 60.00 |
riser |
$ 720.00 |
Pad at door |
1 |
$ 200.00 |
ea. |
$ 200.00 |
Pad at front steps |
1 |
$ 75.00 |
ea. |
$ 75.00 |
Dumpster pad |
80 |
$ 8.00 |
SF |
$ 640.00 |
Sonotube footings for exterior steel stair |
1 |
$ 100.00 |
LS |
$ 100.00 |
Framing, Drywall, Doors & Frames, Windows, Kitchen, Finish
Carpentry, Misc. Metals, Finish Materials |
|
|
|
|
Interior walls |
45 |
$ 30.00 |
LF |
$ 1,350.00 |
Addition walls |
206 |
$ 30.00 |
LF |
$ 6,180.00 |
Second floor joists and sheathing |
432 |
$ 2.25 |
SF |
$ 972.00 |
Roof framing rafters, ceiling joists and sheathing |
1 |
$ 3,500.00 |
LS |
$ 3,500.00 |
Shingles and ice guard underlayment |
1 |
$ 2,000.00 |
LS |
$ 2,000.00 |
Misc. fascia, ridge and collar ties |
1 |
$ 300.00 |
LS |
$ 300.00 |
Add 2 columns in basement |
2 |
$ 50.00 |
ea. |
$ 100.00 |
Infill floor at old basement stair |
1 |
$ 150.00 |
ea. |
$ 150.00 |
Misc. framing, header in dining room, patch & paint |
1 |
$ 700.00 |
LS |
$ 700.00 |
New porch
subflooring on sleepers |
160 |
$ 2.00 |
SF |
$ 320.00 |
Drywall taped and painted |
1200 |
$ 1.50 |
SF |
$ 1,800.00 |
Doors and frames |
17 |
$ 500.00 |
ea. |
$ 8,500.00 |
Paint doors and trim |
17 |
$ 50.00 |
ea. |
$ 850.00 |
Windows |
13 |
$ 400.00 |
ea. |
$ 5,200.00 |
Paint window interior trim |
13 |
$ 30.00 |
ea. |
$ 390.00 |
Kitchen cabinets and counter (HUD spec) |
20 |
$ 300.00 |
LF |
$ 6,000.00 |
Range and hood |
1 |
$ 4,500.00 |
LS |
$ 4,500.00 |
Dishwasher |
1 |
$ 600.00 |
ea. |
$ 600.00 |
Closet rods and shelves |
6 |
$ 50.00 |
ea. |
$ 300.00 |
Steel exit stair |
16 |
$ 175.00 |
riser |
$ 2,800.00 |
Floor finishes allowance |
1400 |
$ 2.50 |
SF |
$ 3,500.00 |
Baseboard moldings |
1 |
$ 800.00 |
LS |
$ 800.00 |
Bathroom finishes allowance |
1 |
$ 2,000.00 |
ea. |
$ 2,000.00 |
Insulation foundation, walls, ceiling |
1 |
$ 600.00 |
LS |
$ 600.00 |
Bathroom accessories |
1 |
$ 100.00 |
ea. |
$ 100.00 |
Siding, fascia and soffit |
|
|
|
|
Siding (new addition only) |
1 |
$ 7,000.00 |
LS |
$ 7,000.00 |
Trim and soffit |
1 |
$ 350.00 |
LS |
$ 350.00 |
Plumbing |
1 |
$ 5,000.00 |
LS |
$ 5,000.00 |
Heating and ventilation |
1 |
$ 5,000.00 |
LS |
$ 5,000.00 |
Electrical |
1 |
$ 6,300.00 |
LS |
$ 6,300.00 |
Subtotal
proposed construction work |
|
|
|
$ 102,127.00 |
Contractor
overhead and profit at 25% |
|
|
|
$ 25,531.75 |
Subtotal |
|
|
|
$ 127,658.75 |
Contingency
at 15% |
|
|
|
$
19,148.81 |
Total
proposed construction work |
|
|
|
$
146,807.56 |
|
|
|
|
|